Skip to content

Angoon Airport Project SFAPT00086

Angoon Logo

Project Schedule

The Alaska Department of Transportation and Public Facilities (DOT&PF) plans to complete airport design and property acquisition in mid-2023 and tentatively anticipates construction bidding shortly thereafter.

Right-of way (ROW) work is underway to identify property owners, and the property appraisal effort is complete. In the coming months, the Angoon Airport Project Team will contact all owners of properties affected by the project. Click here for more about the Angoon Airport ROW process.

Construction is tentatively anticipated to begin in late 2023. Construction work could take up to four years. The first step in the construction of the project will likely be tree clearing before major ground disturbing activity.

Project Timeline

Questions? See the project Contacts page.